Contractor estimate change calculator
See what one proposed addition, credit or replacement would do to the total. Use the amounts on your written estimate and change request. Your entries stay on this page.
Check the proposed total
Use US dollar amounts. Enter an earlier charge or credit only if it was approved and the original amount excludes it. Enter zero when there were no earlier charges or credits.
- Original estimate
- Net earlier approvals
- Current estimate
- Pending change
- Estimate if approved
Example with an added charge
An original estimate of $1,800 plus $75 in earlier approvals is $1,875. A proposed $160 board repair would bring it to $2,035 if approved when all amounts include the same taxes and fees.
What to ask for in writing
- Scope. Which room, item or quantity changed? Which line on the original estimate does it affect?
- Price. What is the new charge and what credit applies to the old line? Which amounts include tax and fees?
- Timing. Which work or finish dates change? What needs approval before the crew proceeds?
If a replacement has one net amount, ask which old line was credited and whether the price already includes that credit. Keep the reply with the existing estimate and any approved changes.
FTC home improvement guidance ยท Wisconsin home improvement guidance
Record one proposed change
Print this section or copy the prompts beside your written estimate.
- Original estimate line and date
- Room, item and change in scope
- New charge, credit and tax basis
- Prior approvals outside original total
- Revised amount if accepted
- Schedule impact and decision status